Action | Validation of ORCA2_ICE_PISCES Reference configuration |
---|---|
PI(S) | Claire Lévy |
Digest | Compare 50 years climatology: existing ORCA2_ICE_PISCES in release 4.0.3 versus trunk using QCO |
Dependencies | If any |
Branch | source:/NEMO/branches/{YEAR}/dev_r{REV}_{ACTION_NAME} |
Previewer(s) | Names |
Reviewer(s) | Names |
Ticket | #XXXX |
Description
Run 50 years climatology ORCA2_ICE_PISCES using release 4.0.3 and the twin simulation using trunk with new QCO. Produce monitoring of the 2 simulation to compare results and validate the trunk (as future release of NEMO).
Implementation
...
Documentation updates
...
Preview
...
Tests
...